Project: East Side Water Reclamation Facility - Phase 2
Value: $16,605,000
Owner: City of Clermont
Engineer: Boyle Engineering Corporation
Description: Work on this project included: modification of existing preliminary treatment structure and existing aeration basins, along with installation of a new Biofilter System, two Anoxic Basins, two Aeration Basins, new Mixed Liquor Splitter Box, two 65’ diameter Secondary Clarifiers, a new RAS/WAS Pump Station, two Chlorine Contact Tanks, one bulk Sodium Hypochlorite Storage Tank, two 2MG Concrete Ground Storage Tanks, a new Vertical Turbine Can Pump Station for reclaimed water distribution, a new 6,000 SF Operations Building, a new 8,000 SF Metal Maintenance Building, and miscellaneous piping, concrete, metals, painting, process equipment and piping installation. Self-performed 85% of the work including piping, concrete, metals, painting, process equipment and piping installation.

East Side Water Reclamation Facility - Phase 2
 