Project: North Sumter Wastewater Plant
Value: $10,407,557
Owner: North Sumter Utility, LLC
Engineer: Farner, Barley Associates, Inc
Description: Design and construction of a new 3.0 MGD De-Nite Carrousel Aeration Treatment Facility including Headworks, two Anoxic/Aeration Trains, two 70’ diameter Clarifiers, two Traveling Bridge Filters, Two Chlorine Contact Chambers, Reuse Storage/Pump Station, two Aerated Sludge Holding Tanks, 2.0 meter Belt Filter Press and Operations Building. Encore self performed 85% of the work including yard piping, concrete, metals, painting, process equipment and piping installation. This project received the 2004 ABC Excellence in Construction Eagle Award, Industrial $10 - $20 million
North Sumter Wastewater Treatment Plant
 
blue line blue line